A can finish a piece of work in 16 days and B can finish it in 12 days. They worked together for 4 days and then A left. B finished the remaining work. For how many total number of days did B works to finish the work completely?
Correct Answer :
9
Solution :
To find the total number of days B worked to finish the work completely, we can break down the problem into simple, logical steps.
Step 1: Determine the rate of work for A and B.
Let the total work be 1 unit.
A can finish the work in 16 days, so A's work rate per day is:
B can finish the work in 12 days, so B's work rate per day is:
Step 2: Find their combined rate of work when working together.
When working together, their combined work rate per day is:
To add these fractions, find the least common multiple (LCM) of 16 and 12, which is 48:
So, together they complete of the work per day.
Step 3: Calculate the work completed in the first 4 days.
They worked together for 4 days, so the amount of work completed is:
Step 4: Find the remaining work.
The remaining work after A leaves is:
Step 5: Calculate the time taken by B to finish the remaining work alone.
B finishes the remaining work at a rate of per day:
Number of days B worked alone =
Step 6: Calculate the total number of days B worked.
B worked for the first 4 days with A, and then worked for another 5 days alone to finish the remaining work.
Total days B worked = .
Therefore, the total number of days B worked is 9.
Access expert-curated educational resources and study materials—completely free.
Create, conduct, and manage professional online assessments with Mindyard. Perfect for teachers and institutes.
Copyright © 2026 Mindyard. All Rights Reserved.