Question Details

A can finish a piece of work in 16 days and B can finish it in 12 days. They worked together for 4 days and then A left. B finished the remaining work. For how many total number of days did B works to finish the work completely?

Options

A

6

B

9

C

4

D

8

Show Answer

Correct Answer :

Option B

9

9

Solution :

To find the total number of days B worked to finish the work completely, we can break down the problem into simple, logical steps.

Step 1: Determine the rate of work for A and B.
Let the total work be 1 unit.
A can finish the work in 16 days, so A's work rate per day is:
116
B can finish the work in 12 days, so B's work rate per day is:
112

Step 2: Find their combined rate of work when working together.
When working together, their combined work rate per day is:
116+112
To add these fractions, find the least common multiple (LCM) of 16 and 12, which is 48:
348+448=748
So, together they complete 748 of the work per day.

Step 3: Calculate the work completed in the first 4 days.
They worked together for 4 days, so the amount of work completed is:
4×748=712

Step 4: Find the remaining work.
The remaining work after A leaves is:
1-712=512

Step 5: Calculate the time taken by B to finish the remaining work alone.
B finishes the remaining work 512 at a rate of 112 per day:
Number of days B worked alone = Remaining WorkB's Rate
Days=5/121/12=5 days

Step 6: Calculate the total number of days B worked.
B worked for the first 4 days with A, and then worked for another 5 days alone to finish the remaining work.
Total days B worked = 4+5=9 days.

Therefore, the total number of days B worked is 9.

Unlock Our Free Library

Access expert-curated educational resources and study materials—completely free.

Discover more resources

You may also like

Mock Tests

View All
  • CTET
  • intermediate
  • No time limit
  • child development and pedagogy, mathematics, social science

  • SSC
  • intermediate
  • 2 hours and 30 mins
  • child development and pedagogy, mathematics, social science

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...