Question Details

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

Options

A

3

B

9

C

27

D

81

Show Answer
Correct Answer

Solution :

The correct option is 9.

To find the standard deviation of the critical path in a PERT (Program Evaluation and Review Technique) network, we use the statistical properties of independent activities along that path.

First, we relate the variance of the critical path to the variances of the individual activities. For a series of independent activities on the critical path, the total variance of the critical path (σp2) is the sum of the variances of each individual activity (σi2) on that path:
σp2=∑i=1nσi2

Here, we are given:
- The number of activities on the critical path, n=9
- The standard deviation of each individual activity, σi=3 for all i

First, we calculate the variance of a single activity:
σi2=32=9

Next, we sum the variances of all 9 activities to find the total variance of the critical path:
σp2=9×9=81

Finally, the standard deviation of the critical path (σp) is the square root of its total variance:
σp=σp2=81=9

Therefore, the standard deviation of the critical path is 9.

Transparent Access on Mindyard

Built for Learners & Educators Alike

Completely free for students. Educators & coaching institutes get 2 months free Pro trial to create tests.

FREE FOR STUDENTS

Practice & Learn Free for Students

Access unlimited practice questions, detailed step-by-step solutions, and exam study materials — completely free for students.

  • Unlimited mock tests & question bank practice
  • Full access to curated study library & formula notes
  • 100% free for students • No credit card required
2 MONTHS FREE TRIAL

Educators & Coaching Institutes

Create and conduct professional online assessments with AI question generation, tab proctoring, and comprehensive batch management.

  • AI question uploader & rapid test generator
  • Anti-cheating tab proctoring & performance reports
  • Full Pro access free for 60 days • No upfront commitment
Discover more resources

You may also like

Mock Tests

View All
  • GATE
  • beginner
  • 3 hours
  • civil engineering

Prepare for GATE 2026 Civil Engineering with the latest question papers, previous year papers, detailed solutions, syllabus, exam pattern, preparation tips, mock tests, and subject-wise study material. Download GATE 2026 CE question papers with solutions in PDF format and boost your preparation for top engineering institutes and PSU recruitment.

  • GATE
  • beginner
  • 3 hours
  • electronics and communication engineering

Prepare effectively for GATE 2026 Electronics & Communication Engineering (EC) with this comprehensive Question Paper with Solutions. This resource includes detailed explanations, concept-wise solutions, previous year paper analysis, and exam-oriented practice to help aspirants strengthen core subjects like Electronic Devices, Analog Circuits, Digital Circuits, Signals & Systems, Network Theory, Control Systems, Electromagnetics, Communications, and more. Perfect for revision, self-assessment, and boosting your GATE 2026 EC preparation strategy.

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...
Ask your own doubt or choose a quick prompt: