Question Details

Aproject consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:

Activity
Immediate predecessor
Estimated duration (weeks)
P
5
Q
1
R Q
2
S P,R
4
T P
6
U S,T
3

If all the activities other than S take the estimated amount of time, the maximum duration (in weeks) of the activity S without delaying the completion of the project is ___________.

Show Answer
Correct Answer
6

Solution :

The correct answer is 6.

To find the maximum duration of activity S without delaying the completion of the project, we must first analyze the project network and determine the critical path and the minimum project completion time when all other activities take their estimated durations.

Let us list all the activities along with their estimated durations:
- Activity P: 5 weeks (Predecessor: None)
- Activity Q: 1 week (Predecessor: None)
- Activity R: 2 weeks (Predecessor: Q)
- Activity S: Predecessors are P and R. Its duration is variable.
- Activity T: 6 weeks (Predecessor: P)
- Activity U: 3 weeks (Predecessors: S and T)

The project is completed when the final activity, U, is completed. Let us trace the different paths through the network that lead to the completion of U:

Path 1: P → T → U
This path does not involve activity S. Its duration is constant and calculated as:
Duration = Duration ( P ) + Duration ( T ) + Duration ( U )
Duration = 5 + 6 + 3 = 14 weeks

Since the duration of Path 1 is 14 weeks and does not depend on S, the overall project completion time cannot be less than 14 weeks. Therefore, the scheduled project duration is 14 weeks.

Now, let us examine the paths that include activity S:

Path 2: P → S → U
The duration of this path is:
Duration = Duration ( P ) + Duration ( S ) + Duration ( U )
Duration = 5 + Duration ( S ) + 3 = 8 + Duration ( S )

To ensure that this path does not delay the project completion beyond 14 weeks, its duration must be less than or equal to 14 weeks:
8 + Duration ( S ) ≤ 14
Duration ( S ) ≤ 6 weeks

Path 3: Q → R → S → U
The duration of this path is:
Duration = Duration ( Q ) + Duration ( R ) + Duration ( S ) + Duration ( U )
Duration = 1 + 2 + Duration ( S ) + 3 = 6 + Duration ( S )

To ensure that this path does not delay the project completion beyond 14 weeks:
6 + Duration ( S ) ≤ 14
Duration ( S ) ≤ 8 weeks

Comparing the two constraints on the duration of S:
- From Path 2: Duration(S) ≤ 6 weeks
- From Path 3: Duration(S) ≤ 8 weeks

To satisfy both conditions and avoid delaying the project, the maximum allowable duration for activity S is the minimum of these limits, which is 6 weeks.

Transparent Access on Mindyard

Built for Learners & Educators Alike

Completely free for students. Educators & coaching institutes get 2 months free Pro trial to create tests.

FREE FOR STUDENTS

Practice & Learn Free for Students

Access unlimited practice questions, detailed step-by-step solutions, and exam study materials — completely free for students.

  • Unlimited mock tests & question bank practice
  • Full access to curated study library & formula notes
  • 100% free for students • No credit card required
2 MONTHS FREE TRIAL

Educators & Coaching Institutes

Create and conduct professional online assessments with AI question generation, tab proctoring, and comprehensive batch management.

  • AI question uploader & rapid test generator
  • Anti-cheating tab proctoring & performance reports
  • Full Pro access free for 60 days • No upfront commitment
Discover more resources

You may also like

Mock Tests

View All
  • GATE
  • intermediate
  • 3 hours
  • mechanical engineering

The GATE 2026 Mechanical Engineering (ME) examination scheduled for 14 February 2026 is one of the most important national-level competitive exams for engineering graduates aspiring for higher education and prestigious career opportunities in PSU and research organizations. Conducted annually at the national level, the GATE Mechanical Engineering paper evaluates candidates on core subjects such as Engineering Mechanics, Thermodynamics, Fluid Mechanics, Strength of Materials, Manufacturing Processes, and Machine Design, along with General Aptitude and Engineering Mathematics. This examination is a gateway for admission into M.Tech/Ph.D. programs at IITs, NITs, IISc, and other top institutions, as well as recruitment in major Public Sector Undertakings (PSUs) like ONGC, NTPC, BHEL, IOCL, and more. The GATE ME 2026 paper will test conceptual understanding, analytical thinking, and problem-solving ability, making strong preparation essential for success. Candidates are advised to practice previous year papers, mock tests, and focus on conceptual clarity for high scoring performance. This exam on 14/02/2026 is a crucial opportunity for mechanical engineering aspirants to secure their future in academia and industry.

  • GATE
  • intermediate
  • 3 hours
  • mechanical engineering

Strengthen your preparation with this GATE 2025 Mechanical Engineering (ME) test, covering core subjects such as thermodynamics, fluid mechanics, strength of materials, theory of machines, and manufacturing engineering. With a well-balanced mix of conceptual and numerical questions, this test helps enhance problem-solving ability and technical understanding. Aligned with the latest exam pattern, it is ideal for improving accuracy, speed, and overall exam readiness.

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...
Ask your own doubt or choose a quick prompt: