B is 20% more efficient than A. If B was 60% more efficient than A, then B could complete the work in 18 days lesser than number of days taken by A. What fraction of work would be left after 12 days, if A and B work together?
Correct Answer :
Solution :
The correct option is:
Step-by-Step Explanation:
Let the efficiency of A be units of work per day.
This means A can complete units of work in one day.
1. Analyze the hypothetical case:
If B was 60% more efficient than A, then B's hypothetical efficiency would be:
units of work per day.
Let the total work to be completed be units.
The number of days taken by A to complete the work is:
The number of days taken by B under the hypothetical efficiency is:
According to the problem, B would take 18 days less than A:
Substitute the values of and into the equation:
Simplify the equation by factoring out :
Since , we have:
Solve for (which represents the total days taken by A):
Thus, A alone can complete the work in 48 days.
Let us assume the total work units.
Then A's efficiency unit per day.
2. Determine the actual case:
B is actually 20% more efficient than A.
So, B's actual efficiency is:
units per day.
Combined efficiency of A and B working together:
units per day.
3. Calculate the work completed and left after 12 days:
Work completed in 12 days by A and B together:
units.
Remaining work left:
units.
Fraction of work left:
Dividing the numerator and denominator by 24:
Access expert-curated educational resources and study materials—completely free.
Create, conduct, and manage professional online assessments with Mindyard. Perfect for teachers and institutes.
Copyright © 2026 Mindyard. All Rights Reserved.