Question Details

Consider two cases as below.

Case 1: A company buys 1000 pieces per year of a certain part from vendor 'X'. The changeover time is 2 hours and the price is Rs. 10 per piece. The holding cost rate per part is 10% per year.

Case 2: For the same part, another vendor 'Y" offers a design where the changeover time is 6 minutes, with a price of Rs. 5 per piece, and a holding cost rate per part of 100% per year. The order size is 800 pieces per year from 'X' and 200 pieces per year from 'Y’.

Assume the cost of downtime as Rs. 200 per hour. The percentage reduction in the annual cost for Case 2, as compared to Case 1 is___________ (round off to 2 decimal places).

Show Answer

Correct Answer :

Correct answer is : 5.32

Given, for case (i)

Q = 1000, C = Rs. 10, r = 10% and Cost of downtime = 200/hr, Change over time = 2 hrs

Then,

T c 1 = 1000 × 10 + 1000 2 × 10 × 10 100 + 200 × 2 = R s . 10900

Case (ii)

800 units are ordered from vendor X then total cost from vendor X, only the units will change other conditions will remain the same as the vendor is the same

T c x = 800 × 10 + 800 2 × 10 × 10 100 + 200 × 2 = R s . 8800

For vendor Y

Q = 200, C = Rs. 5, r = 100% and Cost of downtime = 200/hr, Change over time = 6 minutes

T c y = 200 × 5 + 200 2 × 5 × 100 100 + 200 × 1 10 = R s . 1520

Therefore  T c 2 = 8800 + 1520 = R s . 10320

Now the percentage reduction in cost in case (ii)

% r e d u c t i o n = T c 1 T c 2 T c 1 × 100 = 10900 10320 10900 × 100 = 5.321 %

Since %reduction in EOQ model is more compared to the single order therefore the correct answer will be 8.209%.

Solution :

The correct answer is 5.32.

To find the percentage reduction in the annual cost for Case 2 compared to Case 1, we need to calculate the total annual cost for both scenarios. The total annual cost is composed of three components:
1. Purchase Cost: Calculated as the order size multiplied by the price per piece.
2. Holding Cost: Calculated as the average inventory level multiplied by the holding cost rate per part.
3. Downtime (Changeover) Cost: Calculated as the cost of downtime per hour multiplied by the changeover time in hours.

Let's define the general formula for the total cost:
Tc = (Q×C) + Q2×C×r + (Downtime Cost/hour×Changeover Time)
where:
- Q is the annual order size (pieces per year).
- C is the cost price per piece.
- r is the holding cost rate per year.

Step 1: Calculate the Total Annual Cost for Case 1 (Tc1)
For Case 1, the company buys 1000 pieces per year from vendor X. The parameters are:
- Q=1000 pieces per year
- C=Rs. 10 per piece
- r=10%=0.10
- Changeover time = 2 hours
- Downtime cost = Rs. 200 per hour
Substituting these values into our cost formula:
Tc1 = 1000×10 + 10002×10×0.10 + 200×2
Tc1 = 10000+500+400 = Rs. 10900

Step 2: Calculate the Total Annual Cost for Case 2 (Tc2)
In Case 2, the order size is split between vendor X (800 pieces per year) and vendor Y (200 pieces per year). We calculate the individual costs for each vendor and then sum them up.

Cost from Vendor X (Tcx)
Only the quantity changes to 800; other vendor X specific parameters remain the same:
- Q=800 pieces per year
- C=Rs. 10 per piece
- r=10%=0.10
- Changeover time = 2 hours
Tcx = 800×10 + 8002×10×0.10 + 200×2
Tcx = 8000+400+400 = Rs. 8800

Cost from Vendor Y (Tcy)
The parameters for vendor Y are:
- Q=200 pieces per year
- C=Rs. 5 per piece
- r=100%=1.0
- Changeover time = 6 minutes = 660=0.1 hour
Tcy = 200×5 + 2002×5×1.0 + 200×0.1
Tcy = 1000+500+20 = Rs. 1520

Total Cost for Case 2 (Tc2)
Summing the costs of X and Y:
Tc2 = Tcx + Tcy = 8800+1520 = Rs. 10320

Step 3: Calculate the Percentage Reduction
The percentage reduction in the annual cost from Case 1 to Case 2 is calculated as:
% Reduction = Tc1-Tc2Tc1 × 100
Substituting the total costs:
% Reduction = 10900-1032010900 × 100
% Reduction = 58010900 × 100 5.3211%
Rounding off to two decimal places gives a percentage reduction of 5.32%.

Unlock Our Free Library

Access expert-curated educational resources and study materials—completely free.

Discover more resources

You may also like

Mock Tests

View All
  • GATE
  • intermediate
  • 3 hours
  • mechanical engineering

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...