Solving a task, two agents P and Q can finish the project in 24 days, and the output rate of a third agent R is half of that of P. Working together, P, Q, and R can finish the project in 20 days. Determine the time needed to finish the project if Q and R work together?
Correct Answer :
30 days
Solution :
Correct Answer: The time needed to finish the project if Q and R work together is 30 days.
Step-by-Step Explanation:
Let the total work to be completed be represented as 1 whole unit, or we can work in terms of daily work rates (work done per day).
Let , , and be the work done in one day by agents P, Q, and R, respectively.
Step 1: Calculate the combined daily work rate of P and Q.
P and Q together can finish the project in 24 days. Therefore, their combined 1-day work rate is:
Step 2: Calculate the combined daily work rate of P, Q, and R.
Working together, P, Q, and R can finish the project in 20 days. Their combined 1-day work rate is:
Step 3: Find the daily work rate of agent R ().
Subtracting the rate of (P + Q) from the rate of (P + Q + R):
Taking the LCM of 20 and 24, which is 120:
Step 4: Find the daily work rate of agent P ().
We are given that the output rate of R is half of that of P (). Therefore:
Step 5: Find the daily work rate of agent Q ().
Using :
Taking the LCM of 24 and 60, which is 120:
Step 6: Calculate the combined daily work rate of Q and R ().
Taking the common denominator 120:
Conclusion:
Since Q and R together complete of the project per day, the time required for Q and R to finish the entire project working together is:
Access expert-curated educational resources and study materials—completely free.
Create, conduct, and manage professional online assessments with Mindyard. Perfect for teachers and institutes.
Copyright © 2026 Mindyard. All Rights Reserved.