Question Details

Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a team is equally productive. Working separately, teams A, B, and C can complete a certain job in 40 hours, 50 hours, and 4 hours, respectively.

Two members from team A, three members from team B, and one member from team C together start the job, and the member from team C leaves after 23 hours.

The number of additional member(s) from team B, that would be required to replace the member from team C, to finish the job in the next one hour, is

Options

A

4

B

2

C

1

D

3

Show Answer

Correct Answer :

Option B

2

Solution :

The correct answer is Option 2 (which is 2).

Let's solve this step-by-step by determining the individual work rates of members from each team.

Let the total job be represented as 1 unit of work.

Step 1: Calculate the work rate of one member from each team.

Team A consists of 5 members and takes 40 hours to complete the job.
Work done by Team A in 1 hour = 140
Since there are 5 members in Team A, the work done by 1 member of Team A in 1 hour (WA) is:

WA=15×40=1200 per hour.

Team B consists of 8 members and takes 50 hours to complete the job.
Work done by Team B in 1 hour = 150
Since there are 8 members in Team B, the work done by 1 member of Team B in 1 hour (WB) is:

WB=18×50=1400 per hour.

Team C consists of 10 members and takes 4 hours to complete the job.
Work done by Team C in 1 hour = 14
Since there are 10 members in Team C, the work done by 1 member of Team C in 1 hour (WC) is:

WC=110×4=140 per hour.

Step 2: Calculate the work completed in the first 23 hours.

The initial group working for 23 hours consists of:
- 2 members from Team A
- 3 members from Team B
- 1 member from Team C

Combined hourly rate of this initial group:

Hourly Rate=2×WA+3×WB+1×WC

Hourly Rate=2×1200+3×1400+1×140

Taking a common denominator of 400:

Hourly Rate=4400+3400+10400=17400 per hour.

Work done in 23 hours:

Work done=23×17400=391400

Step 3: Calculate the remaining work.

Remaining Work=1-391400=9400

Step 4: Find the required additional members from Team B.

The remaining work needs to be completed in 1 hour.
After 23 hours, the member from Team C leaves.
Let x be the number of additional members from Team B required to replace the member from Team C.
So, the group working during the final 1 hour consists of:
- 2 members from Team A
- (3 + x) members from Team B

Their total work done in 1 hour must equal the remaining work (9400):

2×WA+(3+x)×WB=9400

Substitute the individual work rates into the equation:

2×1200+(3+x)×1400=9400

Convert 2200 to have the denominator 400:

4400+3+x400=9400

Multiply the whole equation by 400:

4+3+x=9

7+x=9

x=2

Thus, 2 additional members from Team B are required to finish the job in the next one hour.

Unlock Our Free Library

Access expert-curated educational resources and study materials—completely free.

Discover more resources

You may also like

Mock Tests

View All
  • CTET
  • intermediate
  • No time limit
  • child development and pedagogy, mathematics, social science

  • SSC
  • intermediate
  • 2 hours and 30 mins
  • child development and pedagogy, mathematics, social science

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...