Question Details

The COVID-19 pandemic has taken the entire world hostage in less than four months, and the global economy has been hit the hardest with governments across the globe implementing stringent policies including lockdown to control the coronavirus outbreak. The pandemic today presents unprecedented challenges and impediments to businesses in conducting their normal operations. The lockdown across the world has caused delays in the performance of contracts and transactions. Now, the question that arises is whether the current situation can enable parties to a contract to alter their obligations with non-compliance of terms neither being regarded as a "default committed by any party" nor a "breach of contract"? There are certain well-accepted practices for dealing with such extraordinary situations in commercial transactions by the inclusion of force majeure & material adverse effect (MAE) clauses. Determination of the types of circumstances so covered by the force majeure clause contained in a contract is essential. Provisions of force majeure often cover natural disasters like hurricanes, floods, and earthquakes as "acts of God." Other covered events may include war, terrorism, civil disorder, fire, disease medical epidemics or by reasons of applicable laws or regulations. Broadly, the Courts have interpreted the term "Force Majeure" as an event that can neither be anticipated nor controlled by either of the contracting parties. A force majeure clause applies in the context of ongoing contractual arrangements, whereas, an MAE or material adverse change (MAC) clause applies to the allocation of risk in transactions before their closure or completion. Pandemic and related consequences such as government action is a type of event covered by a force majeure clause, however, its impact on the affected party's ability to perform its contractual obligations may vary depending upon contractual terms. It is common for force majeure clauses to specify the impact that the event or circumstances in question must have, in order for the clause to be triggered. References may be made, for example, to the event or circumstances having "prevented", "hindered" or "delayed" performance. These terms require different levels of impact on performance before a party can claim recourse to these clauses. In other words, the force majeure and MAC clauses act as an exception to what would otherwise be treated as a breach of contract. Certain contracts may state that, if a force majeure clause is applied, the contract may automatically be terminated. On the other hand, some contracts may even state that the duty to fulfil the contractual obligation may be suspended for a certain period of time and if the force majeure event is not curbed or treated even after such time, then eventually the contract may be terminated. Though there cannot be a one-size-fits-all solution to this question, and it depends upon how the force majeure clause is worded in a specific contract; and in the absence of the same, applicable laws related to the same will be required to be taken into consideration.

[Excerpt from Business Today, by Ranjana Roy Gawai, April 17, 2020]

Typically, the MAE (Material Adverse Change) provision in an agreement contemplates events which if they occur, or are likely occur, would have a ―materially adverse change or effect on the assets, business, property, liabilities, financial condition, results, operations of the target‖ or that ―affects the ability of the transacting parties to consummate the transaction‖ or the ―validity or enforceability of the transacting parties to its rights and remedies under the transaction documents‖. Which of the following sample clauses in a contract resembles an MAE clause?

Options

A

In the event either party is unable to perform its obligations under the terms of this agreement because of Act of God, strikes, equipment of transmission failure or damage reasonably beyond its control, such party shall not be liable for damages to the other for any damages resulting from such failure to perform…‖

B

Except with respect to payment obligations under this agreement, no party shall be liable for, nor such party shall be considered in breach of this agreement due to, any failure to perform its obligations under this agreement as a result of cause beyond its control, including any earthquake, labour problem, unavailability of supplies…‖

C

Both of the above.

D

None of the above.

Show Answer

Correct Answer :

Option D

None of the above.

Solution :

Correct Answer: None of the above.


Step-by-Step Explanation and Logical Reasoning:


1. Understanding an MAE (Material Adverse Effect / Change) Clause:

As per the provided excerpt, an MAE clause specifically allocates risk in commercial transactions before their closure or completion. It refers to events that materially and adversely affect the assets, business, financial condition, operations, or target entity, or that affect the ability of transacting parties to consummate the transaction or enforce transaction documents.


2. Analyzing Option 1:

Option 1 states: "In the event either party is unable to perform its obligations under the terms of this agreement because of Act of God, strikes, equipment of transmission failure or damage reasonably beyond its control, such party shall not be liable for damages..."

This clause deals with excusing performance and shielding a party from liability due to uncontrollable events ("Act of God", strikes, equipment failure) during an ongoing contract. This is a classic Force Majeure clause, not an MAE clause.


3. Analyzing Option 2:

Option 2 states: "Except with respect to payment obligations... no party shall be liable for, nor such party shall be considered in breach of this agreement due to, any failure to perform its obligations under this agreement as a result of cause beyond its control..."

Similar to Option 1, this clause relieves a party from breach of contract for failure to perform caused by events beyond control (earthquakes, labor problems, etc.). This is also a typical Force Majeure clause.


4. Conclusion:

Both sample clauses given in Option 1 and Option 2 represent Force Majeure clauses rather than Material Adverse Effect (MAE) clauses. Therefore, neither sample clause resembles an MAE clause.


Thus, the correct choice is None of the above.

Unlock Our Free Library

Access expert-curated educational resources and study materials—completely free.

Discover more resources

You may also like

Mock Tests

View All
  • CLAT
  • intermediate
  • 2 hours
  • current affairs, general knowledge, legal reasoning, logical reasoning, quant

  • CLAT
  • intermediate
  • 2 hours
  • current affairs, english, general knowledge, legal reasoning, logical reasoning, quant

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...