Twelve men working for 9 hours a day complete a piece of work in 24 days. In how many days can 8 men working for 12 hours a day complete the same piece of work?

Options

A

24 days

B

27 days

C

21 days

D

28 days

Show Answer

Correct Answer :

Option B

27 days