40 men can complete a work in 30 days. However, if 10 men leave the group, how many days will the group take to complete the work?

Options

A

40

B

35

C

45

D

50

Show Answer

Correct Answer :

Option A

40

40

Solution :

The correct answer/option is 40 (days).

To find the number of days required by the new group to complete the work, we can use the concept of "Man-Days", which represents the total amount of work to be done.
The formula relating the number of men, the number of days, and the total work is:
Total Work=M1×D1
where:
M1 is the initial number of men = 40
D1 is the initial number of days = 30

First, let's calculate the total work in terms of man-days:
Total Work=40×30=1200 man-days

Now, if 10 men leave the group, the new number of men (M2) is:
M2=40-10=30 men

Let the number of days taken by the remaining 30 men to complete the same work be D2.
Since the total work remains constant:
M2×D2=Total Work
30×D2=1200

Solving for D2:
D2=120030=40 days

Therefore, the group will take 40 days to complete the work.

Unlock Our Free Library

Access expert-curated educational resources and study materials—completely free.

Discover more resources

You may also like

Mock Tests

View All
  • CTET
  • intermediate
  • No time limit
  • child development and pedagogy, mathematics, social science

  • SSC
  • intermediate
  • 2 hours and 30 mins
  • child development and pedagogy, mathematics, social science

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...