40 men can complete a work in 30 days. However, if 10 men leave the group, how many days will the group take to complete the work?
Correct Answer :
40
Solution :
The correct answer/option is 40 (days).
To find the number of days required by the new group to complete the work, we can use the concept of "Man-Days", which represents the total amount of work to be done.
The formula relating the number of men, the number of days, and the total work is:
where:
is the initial number of men = 40
is the initial number of days = 30
First, let's calculate the total work in terms of man-days:
Now, if 10 men leave the group, the new number of men () is:
Let the number of days taken by the remaining 30 men to complete the same work be .
Since the total work remains constant:
Solving for :
Therefore, the group will take 40 days to complete the work.
Access expert-curated educational resources and study materials—completely free.
Create, conduct, and manage professional online assessments with Mindyard. Perfect for teachers and institutes.
Copyright © 2026 Mindyard. All Rights Reserved.