A alone can finish the work in 15 hours and B alone can finish the work in 20 hours while C alone can finish the work in N hours. All three worked for 5 hours, after that A left the work and remaining work gets completed in 3 hours. Find the value of N.
Solution :
The correct answer is Option 1: 30.
Step-by-step Explanation:
Let's find the rate of work done per hour by each individual.
Time taken by A alone to finish the work = 15 hours.
Work done by A in 1 hour =
Time taken by B alone to finish the work = 20 hours.
Work done by B in 1 hour =
Time taken by C alone to finish the work = N hours.
Work done by C in 1 hour =
Work done in the first 5 hours:
All three (A, B, and C) worked together for 5 hours.
Combined work done by A, B, and C in 1 hour =
Work done by all three in 5 hours =
Simplifying the fraction inside the parentheses:
So, work done in 5 hours by A, B, and C =
Work done in the remaining 3 hours:
After 5 hours, A left the work. The remaining work was completed by B and C working together for 3 hours.
Combined work done by B and C in 1 hour =
Work done by B and C in 3 hours =
Setting up the total work equation:
Total Work = (Work done in first 5 hours) + (Work done in next 3 hours) = 1
Grouping the terms together:
Find a common denominator for and (which is 60):
Substituting this back into the equation:
Cross-multiplying to solve for N:
Thus, the value of N is 30.
Completely free for students. Educators & coaching institutes get 2 months free Pro trial to create tests.
Access unlimited practice questions, detailed step-by-step solutions, and exam study materials — completely free for students.
Create and conduct professional online assessments with AI question generation, tab proctoring, and comprehensive batch management.
A comprehensive SSC MTS 2026 Mock Test 4 designed to help aspirants strengthen their preparation and improve their performance for the Staff Selection Commission Multi-Tasking Staff examination. This mock test covers all major sections including Numerical and Mathematical Ability, Reasoning Ability and Problem Solving, General Awareness, and English Language and Comprehension. It includes a balanced combination of conceptual, analytical, and exam-oriented multiple-choice questions aligned with the latest SSC MTS syllabus and exam pattern. Ideal for practice, revision, self-evaluation, accuracy improvement, speed enhancement, and effective time management, this mock test helps candidates assess their exam readiness, identify improvement areas, and build confidence for the SSC MTS 2026 examination
A comprehensive SSC MTS 2026 Mock Test 3 designed to help aspirants prepare thoroughly for the Staff Selection Commission Multi-Tasking Staff examination. This mock test covers all important sections including Numerical and Mathematical Ability, Reasoning Ability and Problem Solving, General Awareness, and English Language and Comprehension. It features a carefully curated set of multiple-choice questions that test conceptual understanding, logical reasoning, problem-solving skills, speed, and accuracy in accordance with the latest SSC MTS exam pattern. Ideal for practice, revision, self-assessment, performance evaluation, and time management improvement, this mock test enables candidates to identify strengths and weaknesses while building confidence for the SSC MTS 2026 examination.
Copyright © 2026 Combe Labs Private Limited. All Rights Reserved.