Question Details

A and B can complete a piece of work in 12 days and 18 days respectively. They start working together, but after 4 days, A leaves the work. In how many days will B alone complete the remaining work?

Options

A

7

B

5

C

4

D

8

Show Answer
Correct Answer
D 8

Solution :

The correct answer is 8.

Step 1: Determine the daily work rate of A and B.
Let the total work be represented as 1 unit.
A can complete the work in 12 days, so A's work rate per day is:

112

B can complete the work in 18 days, so B's work rate per day is:

118

Step 2: Calculate the combined work done in the first 4 days.
Working together, the combined work done by A and B in 1 day is:

112+118=3+236=536

In 4 days, the amount of work completed by A and B together is:

4×536=2036=59

Step 3: Find the remaining work.
The remaining work after A leaves is:

1-59=49

Step 4: Calculate the time taken by B to finish the remaining work.
Since B completes 118 of the work in 1 day, the time taken by B alone to complete the remaining 49 of the work is:

Days required=49118=49×18=8 days

Thus, B alone will complete the remaining work in 8 days.

Transparent Access on Mindyard

Built for Learners & Educators Alike

Completely free for students. Educators & coaching institutes get 2 months free Pro trial to create tests.

FREE FOR STUDENTS

Practice & Learn Free for Students

Access unlimited practice questions, detailed step-by-step solutions, and exam study materials — completely free for students.

  • Unlimited mock tests & question bank practice
  • Full access to curated study library & formula notes
  • 100% free for students • No credit card required
2 MONTHS FREE TRIAL

Educators & Coaching Institutes

Create and conduct professional online assessments with AI question generation, tab proctoring, and comprehensive batch management.

  • AI question uploader & rapid test generator
  • Anti-cheating tab proctoring & performance reports
  • Full Pro access free for 60 days • No upfront commitment
Discover more resources

You may also like

Mock Tests

View All
  • SSC
  • intermediate
  • 1 hour and 30 mins
  • english, general awareness, logical reasoning, mathematics

A comprehensive SSC MTS 2026 Mock Test 4 designed to help aspirants strengthen their preparation and improve their performance for the Staff Selection Commission Multi-Tasking Staff examination. This mock test covers all major sections including Numerical and Mathematical Ability, Reasoning Ability and Problem Solving, General Awareness, and English Language and Comprehension. It includes a balanced combination of conceptual, analytical, and exam-oriented multiple-choice questions aligned with the latest SSC MTS syllabus and exam pattern. Ideal for practice, revision, self-evaluation, accuracy improvement, speed enhancement, and effective time management, this mock test helps candidates assess their exam readiness, identify improvement areas, and build confidence for the SSC MTS 2026 examination

  • SSC
  • intermediate
  • 1 hour and 30 mins
  • english, general awareness, logical reasoning, mathematics

A comprehensive SSC MTS 2026 Mock Test 3 designed to help aspirants prepare thoroughly for the Staff Selection Commission Multi-Tasking Staff examination. This mock test covers all important sections including Numerical and Mathematical Ability, Reasoning Ability and Problem Solving, General Awareness, and English Language and Comprehension. It features a carefully curated set of multiple-choice questions that test conceptual understanding, logical reasoning, problem-solving skills, speed, and accuracy in accordance with the latest SSC MTS exam pattern. Ideal for practice, revision, self-assessment, performance evaluation, and time management improvement, this mock test enables candidates to identify strengths and weaknesses while building confidence for the SSC MTS 2026 examination.

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...
Ask your own doubt or choose a quick prompt: