Question Details

A and B can complete a work in 15 days and 10 days, respectively. They started doing the work together but after 2 days, B had to leave, and A completed the remaining work alone. The whole work was completed in ______________ days.

Options

A

10

B

13

C

12

D

11

Show Answer

Correct Answer :

Option C

12

Solution :

The correct option is 12.

Let's break down the solution step-by-step to understand why the whole work was completed in 12 days.

Step 1: Determine the rate of work for A and B.
Let the total work to be completed be represented by 1 unit.
Since A can complete the entire work in 15 days, the work done by A in 1 day is:
W A = 1 15 Similarly, since B can complete the entire work in 10 days, the work done by B in 1 day is:
W B = 1 10

Step 2: Calculate the work done together in the first 2 days.
When working together, the amount of work completed by A and B in 1 day is:
W A + B = 1 15 + 1 10 To add these fractions, we find a common denominator, which is 30:
W A + B = 2 + 3 30 = 5 30 = 1 6 In 2 days, the work completed by both of them together is:
Work done in 2 days = 2 × 1 6 = 1 3

Step 3: Calculate the remaining work.
After 2 days, B leaves. The remaining work to be completed is:
Remaining work = 1 1 3 = 2 3

Step 4: Determine the time taken by A to finish the remaining work alone.
Since A completes 1/15 of the work in one day, the number of days A needs to complete the remaining 2/3 of the work is:
Days taken by A = Remaining work W A = 2 / 3 1 / 15 = 2 3 × 15 = 2 × 5 = 10 days

Step 5: Calculate the total time taken to complete the entire work.
The total time consists of the initial 2 days when A and B worked together, plus the 10 days A worked alone to finish the rest:
Total days = 2 + 10 = 12 days

Unlock Our Free Library

Access expert-curated educational resources and study materials—completely free.

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...