Three cloud servers, X, Y, and Z, working simultaneously can process a large database migration in hours, whereas servers X and Z operating together can complete the same migration in 16 hours. How many hours would server Y take working alone to process 75% of the same database migration?
Correct Answer :
60 hours
Solution :
The correct option is 60 hours.
Step-by-step Explanation:
Step 1: Calculate the combined work rate of servers X, Y, and Z working together.
The three servers X, Y, and Z operating together can complete the database migration in
hours, which converts to an improper fraction as
hours.
The combined work rate of (X + Y + Z) per hour is:
of the total migration work per hour.
Step 2: Calculate the combined work rate of servers X and Z working together.
Servers X and Z operating together can complete the database migration in 16 hours.
The combined work rate of (X + Z) per hour is:
of the total migration work per hour.
Step 3: Determine the work rate of server Y operating alone.
The work rate of server Y is the difference between the combined rate of (X + Y + Z) and the combined rate of (X + Z):
Taking the least common multiple of 40 and 16, which is 80:
Server Y processes
of the database migration per hour.
Step 4: Find the total time server Y takes to complete 100% of the migration alone.
Time required for server Y to complete the full migration =
hours.
Step 5: Calculate the time server Y takes to process 75% of the database migration.
75% of the total migration is equal to:
of the total work.
Time taken by Y to process 75% of the migration =
hours.
Thus, server Y working alone would take 60 hours to process 75% of the database migration.
Access expert-curated educational resources and study materials—completely free.
Create, conduct, and manage professional online assessments with Mindyard. Perfect for teachers and institutes.
Copyright © 2026 Mindyard. All Rights Reserved.