A, B and C together can do a work in 4 days, while B alone can do the same work in 24 days. If efficiency of C is 300% more than that of B, then find the difference between number of days taken by A and C to complete the work alone?
Correct Answer :
18
Solution :
The correct option is 18.
Let's break down the problem step-by-step to find the difference between the number of days taken by A and C to complete the work alone.
Step 1: Understand the given data
Let total work be calculated based on the rate of work done by each person.
B alone can complete the work in 24 days.
Let the work efficiency of B be x units/day.
Therefore, Total Work = Efficiency of B × Time taken by B
Total Work = 24x units
Step 2: Determine the efficiency of C
The efficiency of C is 300% more than that of B.
Efficiency of C = x + 300% of x
Step 3: Determine the efficiency of A
A, B, and C together can finish the work in 4 days.
Now, substituting the efficiencies of B and C into the combined efficiency equation:
Step 4: Calculate the days taken by A and C to finish the work alone
Time taken by A alone =
Time taken by C alone =
Step 5: Find the difference between the number of days taken by A and C
Thus, the difference between the number of days taken by A and C to complete the work alone is 18 days.
Access expert-curated educational resources and study materials—completely free.
Create, conduct, and manage professional online assessments with Mindyard. Perfect for teachers and institutes.
Copyright © 2026 Mindyard. All Rights Reserved.