Question Details

A point ‘P’ on a CNC controlled XY-stage is moved to another point ‘Q’ using the coordinate system shown in the figure below and rapid positioning command (G00).

A pair of stepping motors with a maximum speed of 800 rpm, controlling both the X and Y motion of the stage, are directly coupled to a pair of lead screws, each with a uniform pitch of 0.5 mm. The time needed to position the point ‘P’ to the point ‘Q’ is ______ minutes. (round off to 2 decimal places).

Show Answer
Correct Answer

Correct answer is : 1.5

Given, N = 800 rpm, p = 0.5 mm, Δx = 600, Δy = 300

V = 800 ( r e v m i n ) × 0.5 ( m m r e v ) = 400 m m m i n

Now the time taken to traverse in the x-direction

T = 600 400 = 1.5 m i n

Now the time taken to traverse in the y-direction

T = 300 400 = 0.75 m i n

So the time taken to reach from Point P to point Q will be 1.5 minutes, the motor in the y-direction will stop after 0.75 minutes and the motor in the x-direction will run for 1.5 minutes.

Solution :

The correct answer is 1.5.

Based on the coordinate system shown in the figure, we can identify the coordinates of the two points:
- The starting point P is located at (200, 300).
- The destination point Q is located at (800, 600).

First, we find the required travel distances in the X and Y directions:

Δ x = 800 - 200 = 600 mm

Δ y = 600 - 300 = 300 mm

The motors drive lead screws directly with a pitch of 0.5 mm at a maximum speed of 800 rpm. The maximum linear velocity (feed rate) of the stage along either axis is:

V = Rotational Speed ( N ) × Pitch ( p )

V = 800 rpm × 0.5 mm/rev = 400 mm/min

With G00 (rapid positioning), the X and Y motors control the stage axes independently and simultaneously at their maximum speed. Therefore, we calculate the time taken to travel along each direction separately:

Time taken to traverse in the X-direction:

T x = Δ x V = 600 400 = 1.5 minutes

Time taken to traverse in the Y-direction:

T y = Δ y V = 300 400 = 0.75 minutes

Since both axes move simultaneously, the total positioning time required to move from point P to point Q is determined by the axis that takes the maximum time to reach its coordinate:

T total = max ( T x , T y ) = 1.5 minutes

Thus, the motor for the Y-direction finishes its travel and stops after 0.75 minutes, while the motor for the X-direction continues to run until the total target position is reached at 1.5 minutes.

Transparent Access on Mindyard

Built for Learners & Educators Alike

Completely free for students. Educators & coaching institutes get 2 months free Pro trial to create tests.

FREE FOR STUDENTS

Practice & Learn Free for Students

Access unlimited practice questions, detailed step-by-step solutions, and exam study materials — completely free for students.

  • Unlimited mock tests & question bank practice
  • Full access to curated study library & formula notes
  • 100% free for students • No credit card required
2 MONTHS FREE TRIAL

Educators & Coaching Institutes

Create and conduct professional online assessments with AI question generation, tab proctoring, and comprehensive batch management.

  • AI question uploader & rapid test generator
  • Anti-cheating tab proctoring & performance reports
  • Full Pro access free for 60 days • No upfront commitment
Discover more resources

You may also like

Mock Tests

View All
  • GATE
  • intermediate
  • 3 hours
  • mechanical engineering

The GATE 2026 Mechanical Engineering (ME) examination scheduled for 14 February 2026 is one of the most important national-level competitive exams for engineering graduates aspiring for higher education and prestigious career opportunities in PSU and research organizations. Conducted annually at the national level, the GATE Mechanical Engineering paper evaluates candidates on core subjects such as Engineering Mechanics, Thermodynamics, Fluid Mechanics, Strength of Materials, Manufacturing Processes, and Machine Design, along with General Aptitude and Engineering Mathematics. This examination is a gateway for admission into M.Tech/Ph.D. programs at IITs, NITs, IISc, and other top institutions, as well as recruitment in major Public Sector Undertakings (PSUs) like ONGC, NTPC, BHEL, IOCL, and more. The GATE ME 2026 paper will test conceptual understanding, analytical thinking, and problem-solving ability, making strong preparation essential for success. Candidates are advised to practice previous year papers, mock tests, and focus on conceptual clarity for high scoring performance. This exam on 14/02/2026 is a crucial opportunity for mechanical engineering aspirants to secure their future in academia and industry.

  • GATE
  • intermediate
  • 3 hours
  • mechanical engineering

Strengthen your preparation with this GATE 2025 Mechanical Engineering (ME) test, covering core subjects such as thermodynamics, fluid mechanics, strength of materials, theory of machines, and manufacturing engineering. With a well-balanced mix of conceptual and numerical questions, this test helps enhance problem-solving ability and technical understanding. Aligned with the latest exam pattern, it is ideal for improving accuracy, speed, and overall exam readiness.

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...
Ask your own doubt or choose a quick prompt: