Question Details

A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor(s) are listed in the table. The expected time of the project completion is __________ weeks (in integer).

Activity Time estimates (in weeks) Immediate predecessor(s) Optimistic time Most likely time Pessimistic time A 4 5 6 None B 1 3 5 A C 1 2 3 A D 2 4 6 C E 3 4 5 B, D

Activity Time estimates (in weeks)
Immediate
predecessor(s)
Optimistic
time
Most likely
time
Pessimistic
time
A 4 5 6 None
B 1 3 5 A
C 1 2 3 A
D 2 4 6 C
E 3 4 5 B,D

Show Answer
Correct Answer

Correct answer is : 15

Solution :

The correct answer is 15.

Step 1: Understand the Expected Activity Duration Formula
In project scheduling using PERT (Program Evaluation and Review Technique), the activity durations follow a beta distribution. The expected time (TE) for each activity is calculated using its three-time estimates: optimistic time (to), most likely time (tm), and pessimistic time (tp) by the formula:
TE=to+4tm+tp6

Step 2: Calculate the Expected Time (TE) for Each Activity
Using the table data provided in the question and shown in the image, we compute the expected times for activities A, B, C, D, and E:

  • Activity A (Predecessor: None):
    TE(A)=4+4(5)+66=306=5 weeks
  • Activity B (Predecessor: A):
    TE(B)=1+4(3)+56=186=3 weeks
  • Activity C (Predecessor: A):
    TE(C)=1+4(2)+36=126=2 weeks
  • Activity D (Predecessor: C):
    TE(D)=2+4(4)+66=246=4 weeks
  • Activity E (Predecessors: B, D):
    TE(E)=3+4(4)+56=246=4 weeks

Step 3: Analyze the Network Paths and Project Completion Time
By tracing the predecessors in the network diagram from the image, we can identify all possible paths from the start of the project to its completion:

  1. Path 1 (A → B → E):
    Duration=TE(A)+TE(B)+TE(E)=5+3+4=12 weeks
  2. Path 2 (A → C → D → E):
    Duration=TE(A)+TE(C)+TE(D)+TE(E)=5+2+4+4=15 weeks
The expected project completion time is determined by the critical path, which is the path with the longest total duration. Comparing the two paths:
Project Completion Time=max(12,15)=15 weeks
Thus, the expected time of the project completion is 15 weeks.

Transparent Access on Mindyard

Built for Learners & Educators Alike

Completely free for students. Educators & coaching institutes get 2 months free Pro trial to create tests.

FREE FOR STUDENTS

Practice & Learn Free for Students

Access unlimited practice questions, detailed step-by-step solutions, and exam study materials — completely free for students.

  • Unlimited mock tests & question bank practice
  • Full access to curated study library & formula notes
  • 100% free for students • No credit card required
2 MONTHS FREE TRIAL

Educators & Coaching Institutes

Create and conduct professional online assessments with AI question generation, tab proctoring, and comprehensive batch management.

  • AI question uploader & rapid test generator
  • Anti-cheating tab proctoring & performance reports
  • Full Pro access free for 60 days • No upfront commitment
Discover more resources

You may also like

Mock Tests

View All
  • GATE
  • intermediate
  • 3 hours
  • mechanical engineering

The GATE 2026 Mechanical Engineering (ME) examination scheduled for 14 February 2026 is one of the most important national-level competitive exams for engineering graduates aspiring for higher education and prestigious career opportunities in PSU and research organizations. Conducted annually at the national level, the GATE Mechanical Engineering paper evaluates candidates on core subjects such as Engineering Mechanics, Thermodynamics, Fluid Mechanics, Strength of Materials, Manufacturing Processes, and Machine Design, along with General Aptitude and Engineering Mathematics. This examination is a gateway for admission into M.Tech/Ph.D. programs at IITs, NITs, IISc, and other top institutions, as well as recruitment in major Public Sector Undertakings (PSUs) like ONGC, NTPC, BHEL, IOCL, and more. The GATE ME 2026 paper will test conceptual understanding, analytical thinking, and problem-solving ability, making strong preparation essential for success. Candidates are advised to practice previous year papers, mock tests, and focus on conceptual clarity for high scoring performance. This exam on 14/02/2026 is a crucial opportunity for mechanical engineering aspirants to secure their future in academia and industry.

  • GATE
  • intermediate
  • 3 hours
  • mechanical engineering

Strengthen your preparation with this GATE 2025 Mechanical Engineering (ME) test, covering core subjects such as thermodynamics, fluid mechanics, strength of materials, theory of machines, and manufacturing engineering. With a well-balanced mix of conceptual and numerical questions, this test helps enhance problem-solving ability and technical understanding. Aligned with the latest exam pattern, it is ideal for improving accuracy, speed, and overall exam readiness.

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...
Ask your own doubt or choose a quick prompt: