| Activity | Duration (in weeks) | ||
|---|---|---|---|
| t₀ | tₘ | tₚ | |
| 1–2 | 2 | 4 | 12 |
| 1–3 | 2 | 4 | 6 |
| 1–4 | 3 | 4 | 11 |
| 2–5 | 3 | 6 | 6 |
| 3–4 | 2 | 5 | 14 |
| 3–5 | 3 | 3 | 3 |
| 4–5 | 3 | 6 | 15 |
| 5–6 | 2 | 5 | 8 |
Correct Answer :
Solution :
The correct answer is 22.
To determine the expected project length, we use the Project Evaluation and Review Technique (PERT). First, we calculate the expected duration () for each activity using the standard PERT formula:
where:
is the optimistic time,
is the most likely time, and
is the pessimistic time.
Let's calculate the expected duration for each activity based on the values in the table:
1. Activity 1–2:
weeks
2. Activity 1–3:
weeks
3. Activity 1–4:
weeks
4. Activity 2–5:
weeks
5. Activity 3–4:
weeks
6. Activity 3–5:
weeks
7. Activity 4–5:
weeks
8. Activity 5–6:
weeks
Next, we identify all possible paths from the start node (1) to the end node (6) and calculate their total expected durations:
Path A: 1–2–5–6
Duration = weeks
Path B: 1–3–5–6
Duration = weeks
Path C: 1–3–4–5–6
Duration = weeks
Path D: 1–4–5–6
Duration = weeks
The critical path is the path with the longest expected duration, which is Path C (1–3–4–5–6) with a total expected duration of 22 weeks. Thus, the expected project length is 22 weeks.
Access expert-curated educational resources and study materials—completely free.
Create, conduct, and manage professional online assessments with Mindyard. Perfect for teachers and institutes.
Copyright © 2026 Mindyard. All Rights Reserved.