Question Details

Anirudh and Brahmaji are assigned the work of constructing a wall. Anirudh can do the job in 60 hours alone where as Brahmaji can do the job three times faster. Anirudh starts the work during the first hour and Brahmaji does the work during the second hour. During the third hour both do the job simultaneously. If they continue in this fashion, how long it will take for them to complete the job?

Options

A

21.5 hours

B

22.5 hours

C

23 hours

D

7.5 hours

Show Answer
Correct Answer
C
23 hours

Solution :

The correct option is 23 hours.

Let us break down the problem step-by-step to calculate the total time required to complete the construction of the wall.

Step 1: Determine individual work rates

Let the total work required to construct the wall be 60 units (since Anirudh takes 60 hours).

Anirudh's work rate per hour:
Anirudh takes 60 hours to complete 60 units of work.
Anirudh's rate=60 units60 hours=1 unit/hour

Brahmaji's work rate per hour:
Brahmaji works 3 times faster than Anirudh.
Brahmaji's rate=3×1 unit/hour=3 units/hour

Step 2: Understand the work pattern

The work is carried out in a 3-hour repeating cycle:

Hour 1: Anirudh works alone and completes 1 unit of work.
Hour 2: Brahmaji works alone and completes 3 units of work.
Hour 3: Both work together and complete (1 + 3) = 4 units of work.

Total work completed in one 3-hour cycle:
Work per cycle=1+3+4=8 units

Step 3: Calculate the work completed in full cycles

Total work to complete = 60 units.
Work done in 1 cycle (3 hours) = 8 units.

Let us find how many full 3-hour cycles fit into 60 units:
60÷8=7 cycles with a remainder of 4 units

Time taken for 7 full cycles:
Time=7×3 hours=21 hours

Work completed after 21 hours (7 cycles):
Work done=7×8=56 units

Remaining work = 60 - 56 = 4 units.

Step 4: Calculate time required for the remaining work

Now, we begin the 8th cycle:

22nd Hour (Hour 1 of 8th cycle):
Anirudh works alone and completes 1 unit.
Remaining work = 4 - 1 = 3 units.
Total time so far = 21 + 1 = 22 hours.

23rd Hour (Hour 2 of 8th cycle):
Brahmaji works alone. Brahmaji's rate is 3 units/hour.
Since exactly 3 units of work remain, Brahmaji will complete it in exactly 1 hour.
Remaining work = 3 - 3 = 0 units.
Total time so far = 22 + 1 = 23 hours.

Conclusion:
The wall construction will take a total of 23 hours to complete.

Transparent Access on Mindyard

Built for Learners & Educators Alike

Completely free for students. Educators & coaching institutes get 2 months free Pro trial to create tests.

FREE FOR STUDENTS

Practice & Learn Free for Students

Access unlimited practice questions, detailed step-by-step solutions, and exam study materials — completely free for students.

  • Unlimited mock tests & question bank practice
  • Full access to curated study library & formula notes
  • 100% free for students • No credit card required
2 MONTHS FREE TRIAL

Educators & Coaching Institutes

Create and conduct professional online assessments with AI question generation, tab proctoring, and comprehensive batch management.

  • AI question uploader & rapid test generator
  • Anti-cheating tab proctoring & performance reports
  • Full Pro access free for 60 days • No upfront commitment
Discover more resources

You may also like

Mock Tests

View All
  • SSC
  • intermediate
  • 1 hour and 30 mins
  • english, general awareness, logical reasoning, mathematics

A comprehensive SSC MTS 2026 Mock Test 4 designed to help aspirants strengthen their preparation and improve their performance for the Staff Selection Commission Multi-Tasking Staff examination. This mock test covers all major sections including Numerical and Mathematical Ability, Reasoning Ability and Problem Solving, General Awareness, and English Language and Comprehension. It includes a balanced combination of conceptual, analytical, and exam-oriented multiple-choice questions aligned with the latest SSC MTS syllabus and exam pattern. Ideal for practice, revision, self-evaluation, accuracy improvement, speed enhancement, and effective time management, this mock test helps candidates assess their exam readiness, identify improvement areas, and build confidence for the SSC MTS 2026 examination

  • SSC
  • intermediate
  • 1 hour and 30 mins
  • english, general awareness, logical reasoning, mathematics

A comprehensive SSC MTS 2026 Mock Test 3 designed to help aspirants prepare thoroughly for the Staff Selection Commission Multi-Tasking Staff examination. This mock test covers all important sections including Numerical and Mathematical Ability, Reasoning Ability and Problem Solving, General Awareness, and English Language and Comprehension. It features a carefully curated set of multiple-choice questions that test conceptual understanding, logical reasoning, problem-solving skills, speed, and accuracy in accordance with the latest SSC MTS exam pattern. Ideal for practice, revision, self-assessment, performance evaluation, and time management improvement, this mock test enables candidates to identify strengths and weaknesses while building confidence for the SSC MTS 2026 examination.

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...
Ask your own doubt or choose a quick prompt: