| Job | Due Date | Work remaining |
|---|---|---|
Correct Answer :
Job N & O
Solution :
The correct option is Job N & O.
To determine which jobs have a critical ratio less than unity (1), we first need to understand the definition and formula for the Critical Ratio (CR).
The Critical Ratio is a scheduling rule used to determine the priority of jobs. It is calculated using the following formula:
According to the problem description, the current date (as on the production calendar) is day 20.
Therefore, the formula for each job simplifies to:
Now, we calculate the critical ratio for each job listed in the table:
1. For Job M:
Due Date = 26, Work Remaining = 5
Since 1.2 is greater than 1, Job M has a critical ratio greater than unity.
2. For Job N:
Due Date = 24, Work Remaining = 10
Since 0.4 is less than 1, Job N has a critical ratio less than unity.
3. For Job O:
Due Date = 28, Work Remaining = 10
Since 0.8 is less than 1, Job O has a critical ratio less than unity.
4. For Job P:
Due Date = 31, Work Remaining = 5
Since 2.2 is greater than 1, Job P has a critical ratio greater than unity.
Comparing the calculated critical ratios, we find that Job N (CR = 0.4) and Job O (CR = 0.8) are the jobs that have a critical ratio less than unity.
Access expert-curated educational resources and study materials—completely free.
Create, conduct, and manage professional online assessments with Mindyard. Perfect for teachers and institutes.
Copyright © 2026 Mindyard. All Rights Reserved.