For an assembly line, the production rate was 4 pieces per hour and the average processing time was 60 minutes. The WIP inventory was calculated. Now, the production rate is kept the same, and the average processing time is brought down by 30 percent.As a result of this change in the processing time, the WIP inventory
Solution :
The correct option is decreases by 30%.
To understand why this is correct, we can apply Little's Law from operations management and queueing theory. Little's Law states that the long-term average number of items in a stationary queueing system, which represents the Work-in-Process (WIP) inventory, is equal to the long-term average effective arrival rate (or production rate) multiplied by the average time that an item spends in the system (processing time).
Mathematically, Little's Law is expressed as:
where:
• is the Work-in-Process inventory.
• is the production rate (throughput).
• is the average processing time (flow time).
Let us analyze the initial state of the assembly line:
• Initial production rate,
• Initial processing time,
Using Little's Law, the initial WIP inventory is:
Now, let us analyze the changes made to the assembly line:
• The production rate is kept the same:
• The average processing time is brought down by 30%:
Using Little's Law, the new WIP inventory is:
Since the new WIP inventory is 70% of the initial WIP inventory, the percentage change in the WIP inventory is:
Substitute into the equation:
The negative sign indicates a decrease. Therefore, the WIP inventory decreases by 30% as a direct result of the 30% reduction in processing time while maintaining a constant production rate.
Completely free for students. Educators & coaching institutes get 2 months free Pro trial to create tests.
Access unlimited practice questions, detailed step-by-step solutions, and exam study materials — completely free for students.
Create and conduct professional online assessments with AI question generation, tab proctoring, and comprehensive batch management.
The GATE 2026 Mechanical Engineering (ME) examination scheduled for 14 February 2026 is one of the most important national-level competitive exams for engineering graduates aspiring for higher education and prestigious career opportunities in PSU and research organizations. Conducted annually at the national level, the GATE Mechanical Engineering paper evaluates candidates on core subjects such as Engineering Mechanics, Thermodynamics, Fluid Mechanics, Strength of Materials, Manufacturing Processes, and Machine Design, along with General Aptitude and Engineering Mathematics. This examination is a gateway for admission into M.Tech/Ph.D. programs at IITs, NITs, IISc, and other top institutions, as well as recruitment in major Public Sector Undertakings (PSUs) like ONGC, NTPC, BHEL, IOCL, and more. The GATE ME 2026 paper will test conceptual understanding, analytical thinking, and problem-solving ability, making strong preparation essential for success. Candidates are advised to practice previous year papers, mock tests, and focus on conceptual clarity for high scoring performance. This exam on 14/02/2026 is a crucial opportunity for mechanical engineering aspirants to secure their future in academia and industry.
Strengthen your preparation with this GATE 2025 Mechanical Engineering (ME) test, covering core subjects such as thermodynamics, fluid mechanics, strength of materials, theory of machines, and manufacturing engineering. With a well-balanced mix of conceptual and numerical questions, this test helps enhance problem-solving ability and technical understanding. Aligned with the latest exam pattern, it is ideal for improving accuracy, speed, and overall exam readiness.
Copyright © 2026 Combe Labs Private Limited. All Rights Reserved.