In the Critical Path Method (CPM), the cost-time slope of an activity is given by
Solution :
The correct answer is:
Visual Analysis of the Diagram:
The attached image shows the cost-time relationship for a project activity:
• The vertical axis represents the Cost of the activity, pointing out the Normal Cost (Cn) and the higher Crash Cost (Cc).
• The horizontal axis represents the Time required, indicating the Crash Time (tc) and the longer Normal Time (tn).
• The dashed straight line represents the linear approximation of the cost-time relationship between the normal operating point (tn, Cn) and the crashed operating point (tc, Cc). The slope of this line represents the cost slope.
Explanation of Cost-Time Slope in CPM:
In CPM (Critical Path Method) project scheduling, the cost-time slope (or cost slope) represents the additional cost incurred per unit of time saved by shortening (crashing) the activity duration.
To compress a project schedule, managers target activities on the critical path with the flattest cost slope because they offer the most time savings for the least increase in cost.
Mathematical Derivation:
The slope of a straight line passing through the coordinates (tn, Cn) and (tc, Cc) is calculated as:
Since cost increases as time decreases (Cc > Cn and tc < tn), this slope is negative. We are interested in the absolute magnitude of the rate of cost increase, which gives:
Substituting the descriptive terms:
• Cc − Cn is the Crash Cost − Normal Cost (increase in cost).
• tn − tc is the Normal Time − Crash Time (decrease in time).
Thus, the cost-time slope of an activity is given by:
Completely free for students. Educators & coaching institutes get 2 months free Pro trial to create tests.
Access unlimited practice questions, detailed step-by-step solutions, and exam study materials — completely free for students.
Create and conduct professional online assessments with AI question generation, tab proctoring, and comprehensive batch management.
The GATE 2026 Mechanical Engineering (ME) examination scheduled for 14 February 2026 is one of the most important national-level competitive exams for engineering graduates aspiring for higher education and prestigious career opportunities in PSU and research organizations. Conducted annually at the national level, the GATE Mechanical Engineering paper evaluates candidates on core subjects such as Engineering Mechanics, Thermodynamics, Fluid Mechanics, Strength of Materials, Manufacturing Processes, and Machine Design, along with General Aptitude and Engineering Mathematics. This examination is a gateway for admission into M.Tech/Ph.D. programs at IITs, NITs, IISc, and other top institutions, as well as recruitment in major Public Sector Undertakings (PSUs) like ONGC, NTPC, BHEL, IOCL, and more. The GATE ME 2026 paper will test conceptual understanding, analytical thinking, and problem-solving ability, making strong preparation essential for success. Candidates are advised to practice previous year papers, mock tests, and focus on conceptual clarity for high scoring performance. This exam on 14/02/2026 is a crucial opportunity for mechanical engineering aspirants to secure their future in academia and industry.
Strengthen your preparation with this GATE 2025 Mechanical Engineering (ME) test, covering core subjects such as thermodynamics, fluid mechanics, strength of materials, theory of machines, and manufacturing engineering. With a well-balanced mix of conceptual and numerical questions, this test helps enhance problem-solving ability and technical understanding. Aligned with the latest exam pattern, it is ideal for improving accuracy, speed, and overall exam readiness.
Copyright © 2026 Combe Labs Private Limited. All Rights Reserved.