Question Details

Match the mold elements in the casting process with the most suitable function:


Mold element Function
P Blind riser I Casting with internal cavity
Q Chill II Molten metal reservoir
R Skim bob III Nucleating agent
S Core IV Assisting in faster heat removal from melt
T Insulating sleeve V Removal of impurities
U Inoculant VI Increasing the solidification time

Options

A

P-II, Q-IV, R-V, S-I, T-VI, U-III

B

P-II, Q-V, R-VI, S-I, T-III, U-IV

C

P-V, Q-I, R-VI, S-III, T-II, U-IV

D

P-II, Q-IV, R-I, S-V, T-VI, U-III

Show Answer
Correct Answer
A P-II, Q-IV, R-V, S-I, T-VI, U-III

Solution :

The correct option is P-II, Q-IV, R-V, S-I, T-VI, U-III.

Let us analyze the functions of each mold element in the casting process step-by-step to understand why this mapping is correct:

1. P. Blind riser matches with II. Molten metal reservoir
A riser (or feeder) is a reservoir of molten metal built into a metal casting mold. It supplies liquid metal to the casting cavity to compensate for shrinkage as the metal solidifies. A blind riser is completely enclosed within the mold and is not open to the atmosphere. Thus, its primary function is to act as a molten metal reservoir.

2. Q. Chill matches with IV. Assisting in faster heat removal from melt
Chills are metallic objects placed in the mold cavity to promote rapid heat extraction from specific regions of the casting. By conducting heat away quickly, they assist in faster heat removal from the melt, helping to establish directional solidification and avoid shrinkage defects.

3. R. Skim bob matches with V. Removal of impurities
A skim bob is a chamber or trap designed in the gating system (usually along the runner) to prevent lighter slag, dross, and other impurities from entering the mold cavity. It traps these impurities by exploiting differences in density, thereby ensuring the removal of impurities from the flowing molten metal.

4. S. Core matches with I. Casting with internal cavity
A core is a preformed, insertable shape (often made of sand or metal) placed in the mold cavity to define the internal geometry of the casting. In other words, cores are essential for producing casting with internal cavities.

5. T. Insulating sleeve matches with VI. Increasing the solidification time
An insulating sleeve is placed around a riser to reduce heat loss from the riser to the surrounding molding sand. By keeping the riser hotter for a longer duration, it increases the solidification time of the riser, ensuring that the riser remains molten longer than the casting itself to feed it properly.

6. U. Inoculant matches with III. Nucleating agent
An inoculant is a material added to molten metal just before pouring to act as a nucleating agent. It provides heterogeneous nucleation sites that promote the formation of a fine, uniform grain structure during solidification.

Transparent Access on Mindyard

Built for Learners & Educators Alike

Completely free for students. Educators & coaching institutes get 2 months free Pro trial to create tests.

FREE FOR STUDENTS

Practice & Learn Free for Students

Access unlimited practice questions, detailed step-by-step solutions, and exam study materials — completely free for students.

  • Unlimited mock tests & question bank practice
  • Full access to curated study library & formula notes
  • 100% free for students • No credit card required
2 MONTHS FREE TRIAL

Educators & Coaching Institutes

Create and conduct professional online assessments with AI question generation, tab proctoring, and comprehensive batch management.

  • AI question uploader & rapid test generator
  • Anti-cheating tab proctoring & performance reports
  • Full Pro access free for 60 days • No upfront commitment
Discover more resources

You may also like

Mock Tests

View All
  • GATE
  • intermediate
  • 3 hours
  • mechanical engineering

The GATE 2026 Mechanical Engineering (ME) examination scheduled for 14 February 2026 is one of the most important national-level competitive exams for engineering graduates aspiring for higher education and prestigious career opportunities in PSU and research organizations. Conducted annually at the national level, the GATE Mechanical Engineering paper evaluates candidates on core subjects such as Engineering Mechanics, Thermodynamics, Fluid Mechanics, Strength of Materials, Manufacturing Processes, and Machine Design, along with General Aptitude and Engineering Mathematics. This examination is a gateway for admission into M.Tech/Ph.D. programs at IITs, NITs, IISc, and other top institutions, as well as recruitment in major Public Sector Undertakings (PSUs) like ONGC, NTPC, BHEL, IOCL, and more. The GATE ME 2026 paper will test conceptual understanding, analytical thinking, and problem-solving ability, making strong preparation essential for success. Candidates are advised to practice previous year papers, mock tests, and focus on conceptual clarity for high scoring performance. This exam on 14/02/2026 is a crucial opportunity for mechanical engineering aspirants to secure their future in academia and industry.

  • GATE
  • intermediate
  • 3 hours
  • mechanical engineering

Strengthen your preparation with this GATE 2025 Mechanical Engineering (ME) test, covering core subjects such as thermodynamics, fluid mechanics, strength of materials, theory of machines, and manufacturing engineering. With a well-balanced mix of conceptual and numerical questions, this test helps enhance problem-solving ability and technical understanding. Aligned with the latest exam pattern, it is ideal for improving accuracy, speed, and overall exam readiness.

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...
Ask your own doubt or choose a quick prompt: