P and Q can complete a job in 24 days working together. P can alone complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining job is:
Correct Answer :
64 days
Solution :
The correct option is 64 days.
To find the number of days Q will take to complete the remaining job, we can break the problem down step-by-step using the concept of work rates.
Step 1: Determine the total work
Let us assume the total amount of work is the Least Common Multiple (LCM) of the days given for P and Q together (24 days) and P alone (32 days).
The LCM of 24 and 32 is 96.
So, let the total work be 96 units.
Step 2: Find the individual work rates per day
The combined daily work rate of P and Q working together is:
The daily work rate of P working alone is:
Now, we can find the daily work rate of Q by subtracting P's rate from the combined rate:
Step 3: Calculate the work completed in the first 8 days
P and Q worked together for 8 days. The total work completed during this period is:
Step 4: Find the remaining work
Subtract the completed work from the total work to find what remains:
Step 5: Calculate the time Q takes to finish the remaining work
Since P left, Q has to complete the remaining 64 units of work alone. At Q's rate of 1 unit per day, the time required is:
Thus, Q will take 64 days to complete the remaining job.
Access expert-curated educational resources and study materials—completely free.
Create, conduct, and manage professional online assessments with Mindyard. Perfect for teachers and institutes.
Copyright © 2026 Mindyard. All Rights Reserved.