Question Details

P and Q can complete a job in 24 days working together. P can alone complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining job is:

Options

A

26 days

B

30 days

C

64 days

D

60 days

Show Answer

Correct Answer :

Option C

64 days

Solution :

The correct option is 64 days.

To find the number of days Q will take to complete the remaining job, we can break the problem down step-by-step using the concept of work rates.

Step 1: Determine the total work
Let us assume the total amount of work is the Least Common Multiple (LCM) of the days given for P and Q together (24 days) and P alone (32 days).
The LCM of 24 and 32 is 96.
So, let the total work be 96 units.

Step 2: Find the individual work rates per day
The combined daily work rate of P and Q working together is:

Rate of (P + Q) = 96 24 = 4  units per day

The daily work rate of P working alone is:

Rate of P = 96 32 = 3  units per day

Now, we can find the daily work rate of Q by subtracting P's rate from the combined rate:

Rate of Q = Rate of (P + Q) Rate of P

Rate of Q = 4 3 = 1  unit per day

Step 3: Calculate the work completed in the first 8 days
P and Q worked together for 8 days. The total work completed during this period is:

Work completed = 8  days × 4  units per day = 32  units

Step 4: Find the remaining work
Subtract the completed work from the total work to find what remains:

Remaining work = 96 32 = 64  units

Step 5: Calculate the time Q takes to finish the remaining work
Since P left, Q has to complete the remaining 64 units of work alone. At Q's rate of 1 unit per day, the time required is:

Time taken by Q = Remaining work Rate of Q

Time taken by Q = 64 1 = 64  days

Thus, Q will take 64 days to complete the remaining job.

Unlock Our Free Library

Access expert-curated educational resources and study materials—completely free.

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...