P, Q and R can do a work in 20, 25 & 15 days respectively. P, Q & R started work together and after 4 days P & Q leave the work and after 2 days R leaves the work and P joins again. After 3 days P leaves and Q joins and he completes the remaining work. Find the total time to complete the whole work.
Correct Answer :
days
Solution :
The correct option is days.
Let us calculate the total work and the work efficiencies of P, Q, and R step-by-step.
Step 1: Determine the total work and individual work rates (efficiencies)
The time taken by P, Q, and R to complete the work individually is:
• P = 20 days
• Q = 25 days
• R = 15 days
Let the total work be the Least Common Multiple (LCM) of 20, 25, and 15.
LCM(20, 25, 15) = 300 units.
Now, calculate the units of work done per day (efficiency) by each person:
• Efficiency of P = units/day
• Efficiency of Q = units/day
• Efficiency of R = units/day
Step 2: Calculate work done in each phase
Phase 1: First 4 days (P, Q, and R work together)
Combined daily work rate of (P + Q + R) = 15 + 12 + 20 = 47 units/day.
Work done in 4 days = units.
Phase 2: Next 2 days (P & Q leave, so only R works)
Work done by R in 2 days = units.
Phase 3: Next 3 days (R leaves, P joins again, so only P works)
Work done by P in 3 days = units.
Step 3: Calculate remaining work and time required by Q to complete it
Total work completed so far = 188 + 40 + 45 = 273 units.
Remaining work = 300 - 273 = 27 units.
Now, P leaves and Q joins to complete the remaining work.
Time taken by Q to complete the remaining 27 units = days.
Step 4: Calculate total time taken to complete the whole work
Total time = 4 days + 2 days + 3 days + days
Total time = days.
Thus, the total time required to complete the whole work is days.
Access expert-curated educational resources and study materials—completely free.
Create, conduct, and manage professional online assessments with Mindyard. Perfect for teachers and institutes.
Copyright © 2026 Mindyard. All Rights Reserved.