Question Details

Two software developers, Alice and Bob, can finish a coding project in 17 days, whereas Alice, Bob, and Charlie working together can finish the same project in 12 days. Given that Alice is 60% more efficient than Charlie, calculate the number of days Bob would take to finish the entire project alone.

Options

A

60 days

B

55 days

C

47 days

D

42 days

E

51 days

Show Answer
Correct Answer
E 51 days

Solution :

The correct option is 51 days.

To determine the number of days Bob would take to complete the project alone, we can calculate the work rate (portion of work completed per day) for each person.

Let the total work required to complete the project be 1 unit.
The combined daily work rate of Alice and Bob is:
Alice+Bob=117
The combined daily work rate of Alice, Bob, and Charlie working together is:
Alice+Bob+Charlie=112

Subtracting the rate of Alice and Bob from the combined rate of all three gives Charlie's daily work rate:
Charlie=112-117
Taking the common denominator of 204:
Charlie=17-12204=5204

We are given that Alice is 60% more efficient than Charlie. Therefore, Alice's daily work rate is 160% (or 1.6 times) of Charlie's daily work rate:
Alice=1.60×5204=85×5204=8204

Now, we can isolate Bob's daily work rate by subtracting Alice's work rate from the combined work rate of Alice and Bob:
Bob=(Alice+Bob)-Alice
Bob=117-8204
Converting 117 to have the common denominator 204:
117=12204
So, Bob's daily work rate is:
Bob=12204-8204=4204=151

Since Bob completes 151 of the project each day, the time required for Bob to finish the entire project alone is:
Time taken by Bob=11/51=51 days

Transparent Access on Mindyard

Built for Learners & Educators Alike

Completely free for students. Educators & coaching institutes get 2 months free Pro trial to create tests.

FREE FOR STUDENTS

Practice & Learn Free for Students

Access unlimited practice questions, detailed step-by-step solutions, and exam study materials — completely free for students.

  • Unlimited mock tests & question bank practice
  • Full access to curated study library & formula notes
  • 100% free for students • No credit card required
2 MONTHS FREE TRIAL

Educators & Coaching Institutes

Create and conduct professional online assessments with AI question generation, tab proctoring, and comprehensive batch management.

  • AI question uploader & rapid test generator
  • Anti-cheating tab proctoring & performance reports
  • Full Pro access free for 60 days • No upfront commitment
Discover more resources

You may also like

Mock Tests

View All
  • SSC
  • intermediate
  • 1 hour
  • english, general awareness, general intelligence and reasoning, logical reasoning, quant

SSC CHSL Tier-1 Shift 1 2 July 2024 question paper with answers and detailed solutions. This practice paper covers questions from General Intelligence & Reasoning, General Awareness, Quantitative Aptitude, and English Language as asked in the SSC CHSL Tier-1 examination. Practice the SSC CHSL 2 July 2024 Shift 1 paper to understand the exam pattern, question types, difficulty level, and important topics for upcoming SSC CHSL exams.

  • SSC
  • intermediate
  • 1 hour
  • english, general awareness, general intelligence and reasoning, logical reasoning, quant

SSC CHSL Tier-1 Shift 2 held on 2 July 2024 question paper with answers and detailed solutions. This previous year paper covers General Intelligence & Reasoning, Quantitative Aptitude, General Awareness, and English Language. The SSC CHSL Tier-1 exam was conducted in CBT mode with 100 questions for 200 marks and a 60-minute duration.

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...
Ask your own doubt or choose a quick prompt: