The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship “X < Y, Z” means that X is predecessor of activities Y and Z. The time to complete the activities along the critical path is ________ weeks




Activity Duration (Weeks) Precedence Relationship
A 5 A<B,C,D
B 7 B<E,F,G
C 10 C<I
D 6 D<G
E 3 E<H
F 9 F<I
G 7 G<I
H 4 H<I
I 2 ---

Options

A

17

B

21

C

23

D

25

Show Answer
Correct Answer

Solution :

Correct Answer: The correct option is 23 (or the option corresponding to 23).

Step-by-step Explanation:

To determine the time required to complete the activities along the critical path, we first analyze the precedence relationships and durations of each activity as shown in the project table:
1. Activity A has a duration of 5 weeks and acts as a predecessor to activities B, C, and D (written as A<B,C,D). Since it has no predecessor, it is the starting activity.
2. Activity B (duration 7 weeks) precedes E, F, and G.
3. Activity C (duration 10 weeks) precedes I.
4. Activity D (duration 6 weeks) precedes G.
5. Activity E (duration 3 weeks) precedes H, which (duration 4 weeks) precedes I.
6. Activity F (duration 9 weeks) precedes I.
7. Activity G (duration 7 weeks) precedes I.
8. Activity I (duration 2 weeks) has no successor, indicating it is the final activity of the project.

By tracing the dependencies from the starting activity (A) to the final activity (I), we can identify all possible paths through the network and compute their total durations:

Path 1: A → B → E → H → I
Duration:

5+7+3+4+2=21 weeks

Path 2: A → B → F → I
Duration:

5+7+9+2=23 weeks

Path 3: A → B → G → I
Duration:

5+7+7+2=21 weeks

Path 4: A → C → I
Duration:

5+10+2=17 weeks

Path 5: A → D → G → I
Duration:

5+6+7+2=20 weeks

The critical path is defined as the sequence of dependent tasks that determines the minimum time needed to complete the project, which is the path with the longest total duration.

Comparing the durations of all paths, we find that Path 2 (A → B → F → I) has the maximum duration of 23 weeks. Therefore, the critical path duration is 23 weeks.

Transparent Access on Mindyard

Built for Learners & Educators Alike

Completely free for students. Educators & coaching institutes get 2 months free Pro trial to create tests.

FREE FOR STUDENTS

Practice & Learn Free for Students

Access unlimited practice questions, detailed step-by-step solutions, and exam study materials — completely free for students.

  • Unlimited mock tests & question bank practice
  • Full access to curated study library & formula notes
  • 100% free for students • No credit card required
2 MONTHS FREE TRIAL

Educators & Coaching Institutes

Create and conduct professional online assessments with AI question generation, tab proctoring, and comprehensive batch management.

  • AI question uploader & rapid test generator
  • Anti-cheating tab proctoring & performance reports
  • Full Pro access free for 60 days • No upfront commitment
Discover more resources

You may also like

Mock Tests

View All
  • GATE
  • intermediate
  • 3 hours
  • mechanical engineering

The GATE 2026 Mechanical Engineering (ME) examination scheduled for 14 February 2026 is one of the most important national-level competitive exams for engineering graduates aspiring for higher education and prestigious career opportunities in PSU and research organizations. Conducted annually at the national level, the GATE Mechanical Engineering paper evaluates candidates on core subjects such as Engineering Mechanics, Thermodynamics, Fluid Mechanics, Strength of Materials, Manufacturing Processes, and Machine Design, along with General Aptitude and Engineering Mathematics. This examination is a gateway for admission into M.Tech/Ph.D. programs at IITs, NITs, IISc, and other top institutions, as well as recruitment in major Public Sector Undertakings (PSUs) like ONGC, NTPC, BHEL, IOCL, and more. The GATE ME 2026 paper will test conceptual understanding, analytical thinking, and problem-solving ability, making strong preparation essential for success. Candidates are advised to practice previous year papers, mock tests, and focus on conceptual clarity for high scoring performance. This exam on 14/02/2026 is a crucial opportunity for mechanical engineering aspirants to secure their future in academia and industry.

  • GATE
  • intermediate
  • 3 hours
  • mechanical engineering

Strengthen your preparation with this GATE 2025 Mechanical Engineering (ME) test, covering core subjects such as thermodynamics, fluid mechanics, strength of materials, theory of machines, and manufacturing engineering. With a well-balanced mix of conceptual and numerical questions, this test helps enhance problem-solving ability and technical understanding. Aligned with the latest exam pattern, it is ideal for improving accuracy, speed, and overall exam readiness.

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...
Ask your own doubt or choose a quick prompt: