Question Details

The ratio of efficiencies of workers A and B is 4:3. If A can finish a task in 18 days, in how many days will B finish the same task alone?

Options

A

20 days

B

22 days

C

24 days

D

26 days

Show Answer

Correct Answer :

Option C

24 days

Solution :

Correct Option: 24 days

Step-by-Step Explanation:

1. Understand the given values:
Let the efficiency of worker A be EA and the efficiency of worker B be EB.
We are given that the ratio of efficiencies of A and B is 4:3.

EAEB=43

This means worker A completes 4 units of work per day, while worker B completes 3 units of work per day.

2. Calculate the Total Work:
We are given that A alone can finish the task in 18 days.
Total Work = (Efficiency of A) × (Time taken by A)

Total Work=4×18=72 units

3. Calculate the time taken by B alone:
Now, we need to find how many days worker B will take to complete the total work of 72 units.
Time taken by B = (Total Work) / (Efficiency of B)

Time taken by B=723=24 days

Thus, worker B alone will finish the same task in 24 days.

Unlock Our Free Library

Access expert-curated educational resources and study materials—completely free.

Discover more resources

You may also like

Mock Tests

View All
  • CTET
  • intermediate
  • No time limit
  • child development and pedagogy, mathematics, social science

  • SSC
  • intermediate
  • 2 hours and 30 mins
  • child development and pedagogy, mathematics, social science

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...