Question Details

X people were given a contract for doing a piece of work in 18 days. 2 people did not turn up to work due to sickness, and the rest of the people completed the work in 27 days. What is the value of X?

Options

A

6

B

14

C

10

D

2

Show Answer

Correct Answer :

Option A

6

Solution :

The correct option is 6.

Let us understand the problem step-by-step using the concept of man-days (the total amount of work done). The total work is equal to the product of the number of people and the number of days they work.

Initially, X people were contracted to complete the work in 18 days.
Therefore, the total work can be represented as:
Total Work = X×18 man-days

However, 2 people did not turn up. This means the actual number of people who worked is:
(X-2) people

These remaining people completed the same piece of work in 27 days.
So, the total work can also be represented as:
Total Work = (X-2)×27 man-days

Since the total work remains constant in both cases, we can equate the two expressions:
18X=27(X-2)

Now, let us solve the equation for X:
Divide both sides by 9 to simplify the numbers:
2X=3(X-2)

Expand the right side:
2X=3X-6

Rearrange the equation to isolate X:
3X-2X=6
X=6

Thus, the value of X is 6, indicating that 6 people were initially contracted for the work.

Unlock Our Free Library

Access expert-curated educational resources and study materials—completely free.

Discover more resources

You may also like

Mock Tests

View All
  • CTET
  • intermediate
  • No time limit
  • child development and pedagogy, mathematics, social science

  • SSC
  • intermediate
  • 2 hours and 30 mins
  • child development and pedagogy, mathematics, social science

Ask AI Tutor
5 left
Q1 View Question & Options
AI Tutor is solving this question...
Reading question context & options...