X, Y , and Z can complete a project in 20, 40, and 60 days respectively. X works every day, while Y and Z join X every third day. How long will it take to finish the project?
Correct Answer :
days
Solution :
The correct option is days.
Let's solve the problem step-by-step to understand how long it takes X, Y, and Z to complete the project.
Step 1: Calculate the total work and individual daily work rates
Let the total work be the Least Common Multiple (LCM) of the days taken by X, Y, and Z, which are 20, 40, and 60 days respectively.
LCM(20, 40, 60) = 120 units.
Thus, total work = 120 units.
Now, calculate the work done per day by each person:
Work done by X per day = 120 / 20 = 6 units/day
Work done by Y per day = 120 / 40 = 3 units/day
Work done by Z per day = 120 / 60 = 2 units/day
Step 2: Understand the work pattern
The work happens in a 3-day cycle pattern:
Day 1: Only X works = 6 units
Day 2: Only X works = 6 units
Day 3: X, Y, and Z work together = 6 + 3 + 2 = 11 units
Total work completed in one 3-day cycle:
units
Step 3: Calculate the number of complete 3-day cycles
To find how many full 3-day cycles are required to complete most of the 120 units of work:
cycles with a remainder.
Work done in 5 full cycles (which takes days):
units
Remaining work after 15 days:
units
Step 4: Calculate time taken for the remaining work
On the 16th day (the 1st day of the 6th cycle), only X works.
X's rate of work is 6 units per day.
Time required by X to complete the remaining 5 units of work:
days
Step 5: Total time to complete the project
Total time = 15 days + days = days.
Access expert-curated educational resources and study materials—completely free.
Create, conduct, and manage professional online assessments with Mindyard. Perfect for teachers and institutes.
Copyright © 2026 Mindyard. All Rights Reserved.